Project Development Timeline

COV Logo.png
VFD logo.png
wolf.png


Project Schedule

(Enlarge Project Schedule)

Project Schedule.jpg



Past Events


May 4, 2019

Open House – current Fire Station 1

May 7, 2019

 Valdez Municipal General Election

  • New Fire Station bond proposition approval

April 19, 2019 - 5:30 - 7:30 pm

Open House – current Fire Station 1 Open House Flyer

March 19, 2019 - 7:00 pm

City Council Regular Meeting

  • Bond resolution approval not to exceed $16,000,000 - Approved

March 14, 2019 - 7:00 pm

City Council Work Session

March 13, 2019

 Planning and Zoning Commission Meeting

  • Final public hearing and approval of a conditional use permit for the proposed Fire Station at 401 West Pioneer Drive

February 27, 2019

Planning and Zoning Commission Meeting

  • Public hearing for a conditional use Permit for the proposed Fire Station at 401 West Pioneer Drive

February 13, 2019

Planning and Zoning Commission Meeting

  • Final public hearing and vote for the re-plat of the fire station location
  • Final Plat

January 23, 2019 - 7:00 pm

Planning and Zoning Commission Meeting

January 17, 2019 - 6:00 pm

City Council Work Session

January 8, 2019 - 7:00 pm

Parks and Rec Commission Meeting

  • Capital Facilities discussed the impacts to the Ice Rink and Luke Horning Skate Park with the Parks and Rec Commission.

December 12, 2018 – 6:00 – 8:00 pm

Open House – current Fire Station 1 

Open House Open House 3

December 12, 2018

Stakeholders meeting – Council Chambers

Stakeholder Stakeholder 3 

August 22, 2018

Council Meeting - 7:00 pm

  • Vote on the site for the New Fire Station Facility - motion passed for Skate Park site; item #5 under New Business (the vote happened at approximately 1 hour and 15 minutes into the audio of this meeting) Council Action Summary

May 2, 2018

Council Meeting - 7:00 pm

  • Vote on the purchase of West Egan property - motion failed; item #1 under New Business Council Minutes

April 24, 2018

Winterpark Subdivision Community Open House

  • Discussed West Egan location for the new fire station

April 3, 2018

 Final Draft Report from Bettisworth North Architects

  • This report outlined programming space needs, provided a recommendation on short listed sites and budgetary cost estimates for the short listed sites. Final Report

February 6, 2018

Approval of professional services agreement with Bettisworth North Architects for new fire station programming & site development services.

January 17, 2018

City Council Work Session - 6:00 pm

  • Work Session Packet - outline showing process to complete a new fire station project. Description of the site selection process, presentation of scoring matrix and short listed sites. Work session packet